The question

Where in Germany does a solar + battery plant perform best, and does it pay to let the battery charge from the grid as well as from the solar?

The setup

We took one utility-scale project and placed it in each of the 16 German state capitals:

  • 50 MWac solar PV (about 60 MWp)

  • 10 MW / 20 MWh battery

  • 50 MW grid connection

  • the same technical, market and financial assumptions everywhere

Only two things changed. The first was the location, which gave each city its own PVGIS weather data. The second was the battery’s charging strategy: from solar only, or from solar and the grid. That makes 16 cities × 2 strategies = 32 scenarios.

Unlock the Full Article

You've read a free preview. Enter your name and work email to continue reading the complete post.

We use your email only to understand our audience. No spam, ever.

Want to discuss your next project?

Talk to our team about how FIDgate supports your path to FID.

Contact us
Looping Over Locations with Claude Code: 16 Sites, 32 Scenarios | FIDgate